File #: 21-299    Version: 1
Type: Consent Calendar Status: Passed
File created: 4/1/2021 In control: City Council/Public Financing Authority
On agenda: 4/19/2021 Final action: 4/19/2021
Title: Accept the lowest responsive and responsible bid, approve appropriation of funds and authorize execution of a construction contract with Palp, Inc. dba Excel Paving, in the amount of $1,577,750 for the Edwards - Varsity Tract Water Main Replacement project, CC-1558
Attachments: 1. Att#1 Vicinity Map, CC-1558
REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Oliver Chi, City Manager

PREPARED BY: Sean Crumby, Director of Public Works

Subject:
title
Accept the lowest responsive and responsible bid, approve appropriation of funds and authorize execution of a construction contract with Palp, Inc. dba Excel Paving, in the amount of $1,577,750 for the Edwards - Varsity Tract Water Main Replacement project, CC-1558
body

Statement of Issue:
On March 30, 2021, bids were publically opened for the Edwards - Varsity Tract Water Main Replacement project. City Council action is requested to award the construction contract to Palp, Inc., doing business as Excel Paving, the lowest responsive and responsible bidder.

Financial Impact:
Total funds for the project, including contingency and supplemental expenses, is estimated at $1,950,000. Funds for the project are available in the current fiscal year budget in the Water Master Plan Fund, Account No. 50791006.82100, ($1,779,000). Additionally, staff is requesting an appropriation of $171,000 from the undesignated Prop 42 fund balance to Account No. 21985201.82300 to cover 50% of the milling and overlay costs.

Recommended Action:
recommendation
A) Accept the lowest responsive and responsible bid submitted by Excel Paving in the amount of $1,577,750.00; and,

B) Appropriate $171,000 from the Prop 42 Fund, Account No. 21985201.82300; and,

C) Authorize the Mayor and City Clerk to execute a construction contract in a form approved by the City Attorney.
end

Alternative Action(s):
Reject all bids, or provide staff with alternative action.

Analysis:
Approximately 3,200 lineal feet of new pipeline will be constructed as part of the City's annual water main replacement program for this fiscal year. All of the improvements are proposed within the Edwards - Varsity Tract in seven streets.
Since construction activities will likely further degrade the street pavement condition,...