huntington beach banner
File #: 21-283    Version: 2
Type: Consent Calendar Status: Passed
File created: 3/30/2021 In control: City Council/Public Financing Authority
On agenda: 4/19/2021 Final action: 4/19/2021
Title: Accept the lowest responsive and responsible bid and authorize execution of a maintenance contract with Commercial Waterproofing Systems, Inc. (ERC Roofing and Waterproofing), in the amount of $225,450 for the Slater Pump Station Roof Replacement Project, MSC-534
Attachments: 1. Att#1 MSC-534 Vicinity Map
REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Oliver Chi, City Manager

PREPARED BY: Sean Crumby, Director of Public Works

Subject:
title
Accept the lowest responsive and responsible bid and authorize execution of a maintenance contract with Commercial Waterproofing Systems, Inc. (ERC Roofing and Waterproofing), in the amount of $225,450 for the Slater Pump Station Roof Replacement Project, MSC-534
body

Statement of Issue:
On March 3, 2021, bids were opened electronically for the Slater Pump Station Roof Replacement Project, MSC-534. City Council action is requested to award the maintenance contract to Commercial Waterproofing Systems, Inc., doing business as ERC Roofing and Waterproofing, the lowest and responsible bidder.

Financial Impact:
Total funds for the project, including contingency and supplemental expenses, are estimated at $302,158. Funds for the project are available in Infrastructure Fund, Account No. 31440003.82200.

Recommended Action:
recommendation
A) Accept the lowest responsive and responsible bid submitted by Commercial Waterproofing Systems, Inc., doing business as ERC Roofing and Waterproofing, in the amount of $225,450; and,

B) Authorize the Mayor and City Clerk to execute a maintenance contract in a form approved by the City Attorney.
end

Alternative Action(s):
Reject all bids, or provide staff with an alternative action.

Analysis:
The Slater Pump Station, located at the end of Slater Avenue west of Graham Street and directly adjacent to the East Garden Grove Wintersburg Channel, was constructed in 1964. The building was upgraded in 1980 to include a reinforced concrete block building and a built-up roof system sitting upon a wood frame. The built-up roofing at this building, including five mounted exhaust mufflers, are at the end of their useful life and need to be replaced.

Bids were due electronically on March 3, 2021, with the following results:




BIDDER'S NA...