Statement of Issue:
Plans and specifications for the installation of a traffic control signal at the Heil Avenue Fire Station driveway are in final preparation with advertising anticipated in April 2023. Staff is seeking support to begin the public bidding process.
Funding Source:
The engineer's cost estimate for this project is $380,000, including construction contingency and contract administration. Funds for the project in the amount of $290,000 are budgeted in the Traffic Impact Fee Account No. 20690020.82700. The exact funding shortfall will be known with the opening of the sealed bids. Any additional funding required will be requested with the City Council construction award action.
Recommended Action:
recommendation
Motion to approve the project for the fire station signal installation at the Heil Avenue Fire Station (CC-1673) and find that the project is in general conformance with the approved Fiscal Year 2022/2023 Capital Improvement Program.
end
Alternative Action(s):
Recommend changes to the project.
Analysis:
The Heil Avenue Fire Station driveway (5891 Heil Avenue) was identified in the Fiscal Year 2022/2023 Capital Improvement Program (CIP) for signalization in order to improve the ingress to and egress from the fire station for fire department vehicles. The signal will be a hybrid beacon, which will have two red indications and one yellow indication facing traffic on Heil Avenue. When activated from within the fire station, the signal will start flashing yellow on Heil Avenue as a warning to motorists followed by a steady yellow indication and finally a steady red indication. It is during the steady red that th...