Title: Le Bard Park Improvements Phase II, CC-1668.
Attachments: 1. CC1668 Le Bard Park - Vicinity Map, 2. CC1668 LeBard Park - Plans, 3. CC1668 LeBard Park - Contract Documents, 4. CC1668 Le Bard Park - Eng Estimate, 5. CC1668 Le Bard Park - Presentation
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

PUBLIC WORKS COMMISSION

REQUEST FOR ACTION

 

                                                                                                                                                                                                                  

SUBMITTED TO:                     Chairman and Members of the Commission

 

SUBMITTED BY:                     Sean Crumby, PE, Director of Public Works

 

PREPARED BY:                     Brian Polivka, Contract Administrator

 

Subject:

title

Le Bard Park Improvements Phase II, CC-1668.

body

 

Statement of Issue:

Plans and specifications for improvements at the Le Brad Park tennis courts and clubhouse facility are in final preparation with advertisement for bids expected in February 2023.  Staff is seeking support to begin the public bidding process.

 

Funding Source:

The engineer’s cost estimate for this project is $800,000.  Funds in the amount of $788,881.30 are available in Park Development Impact Fee Account Number 22845017.82900 for the project.  It is expected that an unknown amount of additional funding will be necessary pending receipt of construction bids.  Additional funds as needed will be made available from the Schroeder Park Improvement project Account Number 31440005.82800 for the project. 

 

Recommended Action:

recommendation

Motion to approve the project for the Le Bard Park Improvements Phase II, CC-1668, is in conformance with the previously approved Capital Improvement Program.

end

 

Alternative Action(s):

Deny approval and recommend an alternative action.

 

Analysis:

The Le Bard Park Improvements Phase II project will continue improvements to the Le Bard Park facilities including removal and replacement of the aged and deteriorated tennis courts, demo and remove the existing clubhouse building, providing additional open park greenspace, and revise the adjacent landscape and irrigation.

 

Attachment(s):

1.                     CC1668 Le Bard Park - Vicinity Map

2.                     CC1688 Le Bard Park - Plans

3.                     CC1668 Le Bard Park - Construction Documents

4.                     CC1668 Le Bard Park - Engineer’s Estimate

5.                     CC1668 Le Bard Park - Presentation.