huntington beach banner
File #: 23-223    Version: 1
Type: Consent Calendar Status: Agenda Ready
File created: 3/2/2023 In control: City Council/Public Financing Authority
On agenda: 3/21/2023 Final action:
Title: Accept bid and authorize execution of a construction contract with Aguilar & Calderon Corporation in the amount of $887,541.50 for the Le Bard Park Improvements Project, CC-1668
Attachments: 1. Att #1 - CC1668 Le Bard Park - Vicinity Map, 2. Att #2 - Le Bard Park - Presentation
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Al Zelinka, City Manager

VIA: Sean Crumby, Director of Public Works

PREPARED BY: Brian Polivka, Capital Project Administrator

Subject:
title
Accept bid and authorize execution of a construction contract with Aguilar & Calderon Corporation in the amount of $887,541.50 for the Le Bard Park Improvements Project, CC-1668
body

Statement of Issue:
On March 2, 2023, bids were received for the Le Bard Park Improvements Project, CC-1668. Following a review of the bids, it is requested that the City Council award a construction contract to Aguilar & Calderon Corporation, the lowest responsive and responsible bidder.

Financial Impact:
Total construction cost for the project, including the base bid, contingency and supplemental expenses is $1,065,050. Sufficient funds are budgeted in the FY 2022-2023 Operating Budget; $786,661 is available in the Park Development Impact Fee account number 22845017.82900 and $278,389 is available in Infrastructure Fund account number 31440005.82800 for the project.

Recommended Action:
recommendation
A) Accept the lowest responsive and responsible bid submitted by Aguilar & Calderon Corporation in the amount of $887,541.50; and,

B) Authorize the Mayor and City Clerk to execute a construction contract in a form approved by the City Attorney.
end

Alternative Action(s):
Reject staff recommendation and direct staff to:

A) Reject all bids and rebid the project, or

B) Revise the proposed contract award to Aguilar & Calderon Corporation to increase the project scope to also include the Add Alternate No. 1. This would increase the total project cost to a total of $1,160,945.40. Additional unidentified funding would be required.

Analysis:
The Le Bard Park Improvements Project will replace tennis courts and remove the existing clubhouse building at the park adjacent to the Santa Ana River at Indianapolis Ave. Prior efforts...

Click here for full text