huntington beach banner
File #: 23-075    Version: 1
Type: Consent Calendar Status: Agenda Ready
File created: 1/19/2023 In control: City Council/Public Financing Authority
On agenda: 3/21/2023 Final action:
Title: Accept the lowest responsive and responsible bid and authorize execution of a construction contract with All American Asphalt in the amount of $4,385,950 for the Residential Zone 2 Overlay Project, CC-1701
Attachments: 1. Att #1 - Zone 2 Overlay Vicinity Map, 2. Att #2 - Zone 2 residential overlay powerpoint
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

REQUEST FOR CITY COUNCIL ACTION

 

SUBMITTED TO:                     Honorable Mayor and City Council Members                     

 

SUBMITTED BY:                     Al Zelinka, City Manager                     

 

VIA:                     Sean Crumby, Director of Public Works

 

PREPARED BY:                     Max Olin, Contract Administrator

 

Subject:

title

Accept the lowest responsive and responsible bid and authorize execution of a construction contract with All American Asphalt in the amount of $4,385,950 for the Residential Zone 2 Overlay Project, CC-1701

body

 

Statement of Issue:

On January 12, 2023, bids were publically opened for the Residential Zone 2 Overlay Project.  City Council action is requested to award the construction contract to All American Asphalt, the lowest responsive and responsible bidder and encumber additional funds for the replacement of concrete curb and gutter and sidewalk.

 

Financial Impact:

The total cost of the project is $7,247,569. This total includes the construction contract of $4,385,950 plus ten (10%) construction contingency of $439,050, supplemental expenses of $200,000 for construction management and inspection. Also, an additional $1,500,000 in concrete work will be performed by a separate contractor under a current maintenance services contract.

Funds for a majority of this project are available in the current fiscal year budget in the Measure “M” Account 21390029.69365 ($65,000), Gas Tax Account 20790060.82300 ($2,479,182), Prop 42 Account 21990418 ($53,387), Infrastructure Fund Account 31440101.82000 ($2.400.000) Water Fund Account 50685201.82100 ($150,000) and Sewer Fund Account 51185101.82300 ($100,000). Furthermore, staff is requesting an additional appropriation of $2,000,000 in HB Recovery Funds for the remaining difference.

 

Recommended Action:

recommendation

A)  Accept the lowest responsive and responsible bid submitted by All American Asphalt construction company in the amount of $4,385,950; and,

 

B)  Appropriate $2,000,000 in HB Recovery Funds to Infrastructure Fund Account 31490022.82300, and,

 

C)  Authorize the Mayor and City Clerk to execute a construction contract in a form approved by the City Attorney.

 

end

 

Alternative Action(s):

Reject all bids and direct staff to re-scope the project by reducing project cost and complete half of residential zone 2 maintenance by appropriating $2,750,000. Complete the remaining half of residential Zone 2 by adding this work to the next zone in the fiscal year 2023-2024.

 

Analysis:

This project will rehabilitate the pavement for approximately 120 of the worst residential street segments in Maintenance Zone 2 which is the last zone of the 12 Maintenance Zone Program. Maintenance Zone 2 is bounded by Garfield Avenue to the north, The Talbert Channel/City Boundary to the east, Hamilton Avenue to the south, and Bushard Street to the west. Work will include limited localized pavement repairs, crack sealing, cold milling, striping, and an asphalt overlay. The additional concrete work includes the removal and replacement of the most damaged areas of curb and gutter, sidewalk, and driveway approaches. Bids were publicly opened on January 12, 2023, with the following results:

 

BIDDER'S NAME

BID AMOUNT

All American Asphalt

$5,816,400.00

Hardy & Harper

$6,166,188.00

Excel Paving

$6,495,430.00

RJ Noble Company

$6,983,030.00

All American Asphalt has provided acceptable experience on similar projects in the past. In addition, due to budgetary constraints, the original bid from All American Asphalt was reduced by converting some streets from overlay to slurry resulting in an approximately $1,400,000 savings.  Therefore, staff recommends awarding a contract to All American Asphalt in the amount of $4,385,950.

The original engineers estimate was prepared approximately a year and a half ago and due to the escalation of the price for asphalt and concrete the project is much more expensive than originally budgeted.  In addition, there was a lot more concrete work required in this zone than previous zones which also necessitated additional budget.

The total cost of the project, including contingency and supplemental expenses, is as follows:

Project Costs:

 

Construction Contract

$4,385,950

Construction Contingency (10%)

$439,050

Soft Cost (Design, Construction Management)

$200,000

Concrete

$1,500,000

Total

$7,247,569

 

 

Sources of funds for the project are as follows:

Measure “M” Account 21390029.69365

$65,000

Gas Tax Account 20790060.82300

$2,479,182

Prop 42 Account 21990418.82300

$53,387

Infrastructure Fund Account 31440101.82000

$2,000,000

Water Fund Account 50685201.82100

$150,000

Sewer Fund Account 51185101.82300

$100,000

Total

$4,847,569

 

 

Appropriation Requested

$2,000,000

 

 

Environmental Status:

The project is categorically exempt pursuant to Class 1, Section 15301(c) of the California Environmental Quality Act.

 

Strategic Plan Goal:

 Infrastructure & Parks

 

Attachment(s):

1.                     Vicinity Map

2.                     PowerPoint Presentation