REQUEST FOR CITY COUNCIL ACTION
SUBMITTED TO: Honorable Mayor and City Council Members
SUBMITTED BY: Sean Joyce, Interim City Manager
VIA: Sean Crumby, Director of Public Works
PREPARED BY: Joseph Fuentes, Senior Civil Engineer
Subject:
title
Accept the lowest responsive and responsible bid, approve appropriations, and authorize execution of a construction contract with All American Asphalt in the amount of $5,945,346.20 for the FY 21/22 Arterial Rehabilitation Project, CC-1639
body
Statement of Issue:
On May 26, 2022, bids were publicly opened for the FY 21/22 Arterial Rehabilitation Project. City Council action is requested to award the construction contract to All American Asphalt, the lowest responsive and responsible bidder.
Financial Impact:
Funds for this project in the amount of $5,020,000 are available in the Capital Improvement Program (CIP) budget. The cost for the project including contingency is estimated at $6,614,880. Funding to undertake the project (design, construction, etc.) is recommended as follows:
Funding Source Status Amount ($)
Infrastructure Fund CIP $220,000
(Acct 31490007.82300)
RMRA Fund CIP $4,800,000
(Acct 124790004.82300)
Measure M Requested appropriation $1,400,000
Prop 42 Requested appropriation $194,880
Total $6,614,880
Recommended Action:
recommendation
A) Accept the lowest responsive and responsible bid submitted by All American Asphalt in the amount of $5,945,346.20; and,
B) Appropriate $1,400,000 from the Measure M Fund to account 21390032.82300; and,
C) Appropriate $194,880 from the Prop 42 Fund to account 21990008.82300; and,
D) Authorize the Mayor and City Clerk to execute a construction contract in a form approved by the City Attorney.
end
Alternative Action(s):
Reject all bids, and provide staff with direction.
Analysis:
This project will rehabilitate approximately 2 miles of arterial streets. The streets included within the project include:
• Brookhurst Street: Yorktown to Adams
• Adams Avenue: Lake to Main
• Newland Street: Talbert to Slater
• Springdale Street: Warner to Slater
• Warner Avenue: Algonquin to Brightwater
All streets will have new pavement, utilities adjusted to grade, traffic loops and striping. Improvements also include limited replacement of concrete curb, gutter, sidewalk, driveway approaches, access ramps, and trees. The five street segments have been chosen per the Pavement Management Plan and have average Pavement Condition Indexes (PCIs) between 37 (Very Poor) to 75 (Good), warranting rehabilitation.
This project uses a sustainable paving material, Rubberized Asphalt Concrete (RAC), which contains crumb rubber derived from 100% California waste tire rubber. A 2-inch layer of RAC includes over 2,000 waste tires per lane mile. This project will divert approximately 20,000 waste tires that would otherwise end up in a landfill. Including this project, the use of RAC in the rehabilitation of the City’s arterial streets has resulted in the diversion of more than 383,000 waste tires. Reimbursement from the CalRecycle RAC grant in the amount of $42,000 is anticipated upon project completion.
Bids were opened on May 26, 2022, with the following results:
BIDDER'S NAME |
BID AMOUNT |
All American Asphalt |
$5,945,346.20 |
R.J Noble Company |
$6,548,166.40 |
Hardy & Harper, Inc. |
$6,527,973.48 |
Staff recommends awarding a contract to All American Asphalt in the amount of $5,945,346.20. All American Asphalt has successfully completed similar arterial construction projects in the City. The total project cost is estimated to be $6,614,881, which includes the construction contract, construction contingency, inspection, and supplemental services (soils and materials testing.)
Public Works Commission Action:
The Public Works Commission reviewed and approved CC-1639 on March 16, 2022.
Environmental Status:
The project is categorically exempt pursuant to Class 1, section 15031c of the California Environmental Quality Act.
Strategic Plan Goal:
Infrastructure & Parks
Attachment(s):
1. Vicinity Map