Title: Review and Recommend Additional Expenditures for MSC-520, Youth Shelter ADA Improvements and Roof Replacement.
Attachments: 1. List of Change Orders.pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

PUBLIC WORKS COMMISSION

REQUEST FOR ACTION

 

                                                                                                                                                                                                                  

SUBMITTED TO:                     Chairman and Members of the Commission

 

SUBMITTED BY:                     Travis K. Hopkins, PE, Director of Public Works

 

Subject:

title

Review and Recommend Additional Expenditures for MSC-520, Youth Shelter ADA Improvements and Roof Replacement.

body

 

Statement of Issue:

During the construction of MSC-520, Youth Shelter ADA Improvements and Roof Replacement, the contractor has encountered latent and subsurface conditions which require change orders in excess of the standard 10% contingency. Staff is requesting review and recommendation to increase the contingency from 10% to 20%. This is an increase of $35,745, from $35,745 to $71,490.

 

Funding Source:

Funds in the amount of $72,099 are available in the project business unit, account 21580302.82800, Youth Shelter Project, Other Improvements.

 

Recommended Action:

recommendation

Recommend the approval of the additional contingency amount to City Council.

end

 

Alternative Action(s):

Do not recommend the approval and direct staff to plan differently.

 

Analysis:

On November 19, 2018 City Council awarded a contract in the amount of $357,448 to Thomco Construction, Inc. for construction of ADA improvements and roof replacement at the Youth Shelter, a project reviewed by this Commission on September 19, 2018. While constructing the project the contractor has encountered unforeseen subsurface conditions that require the execution of change orders that exceed the standard 10% contingency amount of $35,745.

 

To date there are five approved change orders totaling $33,077.77, and there are a four additional pending change orders that total to $37,596.49, for total change orders of $70,674.26. Attachment 1 is a list of all the change orders. Extra work required includes the removal of existing plaster ceiling to place structural beam and build new bearing wall, extensive remediation of water damage exposed during routine demolition of surface elements, and additional ADA elements. To complete the project and minimize disruption to Youth Shelter operations, staff is requesting the Commission’s recommendation to City Council to spend up to an additional $35,745 in contingency funds for a total contingency of $71,490, which is 20% of the contract amount. The total contract expense, including all contingency, will increase to $428,938, which is within the original architect’s estimate of $435,000 for construction costs.

 

Attachment(s):

1.                     Change Order List