Title: Approve one of the two conceptual design options for the Edison Park Reconfiguration Conceptual Plan and authorize staff to move forward by initiating either a phased or complete development of the design and bid package for construction of the updated facility
Attachments: 1. Att #1 Geotechnical Report 06-07-2021, 2. Att #2 - Community Input, 3. Att #3 Conceptual Plan Diagram CC Approved 11-16-2021, 4. Att #4 - Tree Preservation Report 6-18-2022, 5. Att #5 - Aerial Topographical Survey 6-2022, 6. Att #6 Noise Impact Study 12-15-2023, 7. Att #7 Geophysical Testing Oil Well Locations 7-27-2023, 8. Att #8 Additional Geotechnical Analysis 11-30-2023, 9. Att #9 Proposed Reconfig. Plan CLS Approved 3-12-2025, 10. Att #10 Proposed Reconfig. Plan Option 2 1-5-2026, 11. Att #11 CEQA Environmental Compliance Checklist 2-2026, 12. Att #12 Proposed Phased Reconfig. Plan CLS Approved 3-12-2025, 13. Att #13 Proposed Phased Reconfig. Plan Option 2 1-5-2026, 14. 3/2 SC - 13 Emails, 15. 3/2 SC #21 - Edison Park Reconfiguration Conceptual Plan - A. Wysocki Memo, 16. 3/2 SC #21 - REVISED Att #9 - Commission Approved Concept Plan (2025-02-26), 17. 3/2 SC #21 - REVISED Att #10 - Option 2 Concept Plan (2026-02-26), 18. 3/2 SC #21 - REVISED Att #12 - Commission Approved Concept Plan Phasing (2025-02-26), 19. 3/2 SC #21 - REVISED Att #13 - Option 2 Concept Plan Phasing (2026-02-26), 20. 3/2 SC #21 - Edison Park Proposed Improvements PPT, 21. 3/3 SC - 2 Emails
REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Travis Hopkins, City Manager

VIA: Ashley Wysocki, Director of Community & Library Services

PREPARED BY: Ashley Wysocki, Director of Community & Library Services

Subject:
title
Approve one of the two conceptual design options for the Edison Park Reconfiguration Conceptual Plan and authorize staff to move forward by initiating either a phased or complete development of the design and bid package for construction of the updated facility
body

Statement of Issue:
Staff has worked with RJM Design Group to conduct a robust public input process and develop a conceptual plan to make needed improvements at Edison Community Park (Edison Park). The Community & Library Services Commission (Commission) met on March 12, 2025, and recommended City Council approve the presented design concept. Based on subsequent community input received, staff is presenting two conceptual plan design options for City Council consideration.

Financial Impact:
A total of $4,352,000 in funding is currently available in the FY 2024/25 Capital Improvement Program (CIP) budget through a combination of Park Development, Quimby, and AES sources.

Recommended Action:
recommendation
Approve one of the two conceptual design options for the Edison Park reconfiguration plan and authorize staff to move forward by initiating either a phased or complete development of the design and bid package for construction of the updated facility.

* Option 1: Conceptual Plan presented to the Community & Library Services Commission
* Option 2: Conceptual Plan based on subsequent community input received
end

Alternative Action(s):
Do not approve the recommended action, and direct staff accordingly.

Analysis:
Edison Park, located at 21377 Magnolia Avenue, was constructed in the early 1970's and was opened to the public in 1974. Since that time, the 40-acre park has functioned as one of the City's main re...

Click here for full text