Title: Accept bid and authorize execution of a construction contract with Beador Construction Company, Inc. in the amount of $4,565,300 for the Admiralty Drive Bridge Rehabilitation Project, CC-1450; approve the appropriation of $2,100,000 from the Measure M undesignated fund balance; and authorize 15% in contingency funds
Attachments: 1. Att #1 Location Map, 2. Att #2 Bid Summary, 3. Att #3 PowerPoint Presentation
EQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Eric G. Parra, Interim City Manager

VIA: Chau Vu, Director of Public Works

PREPARED BY: Jonathan Claudio, Senior Civil Engineer

Subject:
title
Accept bid and authorize execution of a construction contract with Beador Construction Company, Inc. in the amount of $4,565,300 for the Admiralty Drive Bridge Rehabilitation Project, CC-1450; approve the appropriation of $2,100,000 from the Measure M undesignated fund balance; and authorize 15% in contingency funds
body

Statement of Issue:
On October 19, 2023, bids were opened for the construction of the Admiralty Drive Bridge Rehabilitation Project, CC-1450 ("Project"). City Council action is requested to award the construction contract to Beador Construction Company, Inc. ("Beador"), the lowest responsive and responsible bidder.

Financial Impact:
The estimated project cost is $5,880,000 which includes the construction contract with Beador, a 15% contingency, and supplemental expenses. The Project budget includes $3,280,000 of federal grant funds in the Highway Bridge Replacement & Rehab Account No. 96185001.82800 and $500,000 from the Infrastructure Fund in Account No. 31440005.82300. An additional budget appropriation of $2,100,000 from the Measure M undesignated fund balance is necessary to award the contract and proceed with construction of the Project.

Recommended Action:
recommendation
A) Accept the lowest responsive and responsible bid submitted by Beador Construction Company, Inc. in the amount of $4,565,300; and

B) Approve the budget appropriation of $2,100,000 from the Measure M (213) undesignated fund balance to a new account to be created under Finance Department guidelines; and

C) Authorize the Director of Public Works to approve up to a 15% contingency in potential construction change orders; and

D) Authorize the Mayor and City Clerk to execute a construction contract with Beador Con...