Legislation Details

File #: 23-456   
Type: Consent Calendar Status: Passed
File created: 5/17/2023 In control: City Council/Public Financing Authority
On agenda: 7/18/2023 Final action: 7/18/2023
Title: Accept the lowest responsive and responsible bid, and authorize execution of a construction contract with R.J. Noble in the amount of $4,137,704.00 for the Banning Avenue Street Improvements, CC-1711.
Attachments: 1. Att #1 CC-1711 - Banning Ave Vicinity Map, 2. Att #2 PPT Banning Improvements 2023 R2, 3. 7/18 Sup Com - Revised PPT
REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Al Zelinka, City Manager

VIA: Alvin Papa, Acting Director of Public Works

PREPARED BY: Joseph Fuentes, Senior Civil Engineer

Subject:
title
Accept the lowest responsive and responsible bid, and authorize execution of a construction contract with R.J. Noble in the amount of $4,137,704.00 for the Banning Avenue Street Improvements, CC-1711.
body

Statement of Issue:
On May 25, 2023, bids were publicly opened for the Banning Avenue Street Improvements Project, CC-1711. City Council action is requested to award the construction contract to R.J. Noble, the lowest responsive and responsible bidder.

Financial Impact:
Total cost for the project is $4,651,473.65 with the breakdown as follows:
Construction - Base Bid
$
3,487,004.00
Construction - Additive Alternative D (Street Lighting)
$
650,700.00
Contingency (10%)
$
413,770.40
Inspection Services
$
77,615.25
Geotechnical Testing
$
22,384.00
TOTAL PROJECT COST
$
4,651,473.65

Funds for this project are available in the current fiscal budget as follows:
RMRA
Acct.
124790006.82300

$
2,700,000.00
Infrastructure Funds
Acct.
31490018.82000

$
100,000.00
AES
Acct.
128485001.82800

$
1,700,000.00
Infrastructure Funds
Acct.
31490016.82300

$
151,473.65
TOTAL FUNDS AVAILABLE
$
4,651,473.65

Recommended Action:
recommendation
A) Accept the lowest responsive and responsible bid submitted by RJ Noble in the amount of $4,137,704.00 (Base Bid + Additive Alternative D); and

B) Authorize the Mayor and City Clerk to execute a construction contract in a form approved by the City Attorney.

end

Alternative Action(s):
1. Reject all bids and reevaluate project scope; or
2. Award Banning Avenue with the base bid, no roundabout, and no additional street lights, in the amount of $3,487,004.00 (Base Bid); or
3. Award Banning Avenue with the base bid, the roundabout, and additional street lights, in the amount of $5,720,372...

Click here for full text