Title: Accept the lowest responsive and responsible bid and authorize execution of a construction contract with Vido Artukovich & Son, Inc./Vidmar, Inc., a JV, in the amount of $4,495,550 for the McFadden Sewer Lift Station, Wet Well Project Phase 2, (CC1610); Reject bids 1-3; Authorize a 15% in contingency; and Authorize appropriation of additional funds
Attachments: 1. Att #1 Construction Contract, 2. Att #2 RCA Contract Agreement Summary, 3. Att #3 PowerPoint Presentation
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Travis Hopkins, City Manager

VIA: Chau Vu, Director of Public Works

PREPARED BY: Michael Aguas, Capital Projects Administrator

Subject:
title
Accept the lowest responsive and responsible bid and authorize execution of a construction contract with Vido Artukovich & Son, Inc./Vidmar, Inc., a JV, in the amount of $4,495,550 for the McFadden Sewer Lift Station, Wet Well Project Phase 2, (CC1610); Reject bids 1-3; Authorize a 15% in contingency; and Authorize appropriation of additional funds
body

Statement of Issue:
On October 21, 2025, the City of Huntington Beach publicly opened bids for the McFadden Sewer Lift Station Wet Well Project Phase 2, CC1610. Shortly thereafter, on November 21, 2025, a formal bid protest was submitted to the Public Works Department. Following a thorough investigation, it was determined that the bids in question did not meet the required contract specifications. In light of these findings, City Council action is requested to award the construction contract to Vido Artukovich & Son, Inc./Vidmar, Inc., a JV, identified as the lowest responsive and responsible bidder.

Financial Impact:
The total project cost is $5,818,625.10, which includes the construction contract with Vido Artukovich & Son Inc./Vidmar, Inc., a JV in the amount of $4,495,550, a 15% construction contingency of $674,332.50, and supplemental expenses of $648,742.60.

The available funding for this project is $1,462,325.01 from the Sewer Service Fund (511) in Account No. 51189027.82600. Additional new funding of $651,039.74 and reappropriation of existing funding in the amount of $3,705,260.35, totaling $4,356,300.09 is requested to be appropriated to fund this project from the Sewer Service Fund (511).

Staff identified savings in the current fiscal year budget in the amount of $3,705,260.35 from the Sewer Service Fund (511) as follows:

Savings from
Account N...