huntington beach banner
File #: 24-538   
Type: Consent Calendar Status: Passed
File created: 7/24/2024 In control: City Council/Public Financing Authority
On agenda: 8/6/2024 Final action: 8/6/2024
Title: Approve and authorize Service Agreements with ECB Solutions, LLC and MVA Power, Inc. for the purchase of electrical switchgear and transformer equipment for the Central Library and authorize appropriation in the amount of $221,494
Attachments: 1. Att #1 ECB Service Agreement, 2. Att #2 MVA Service Agreement Signed by Chau, 3. Att #3 PowerPoint Presentation

REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Eric G. Parra, Interim City Manager

VIA: Chau Vu, Director of Public Works

PREPARED BY: Max Olin, Capital Projects Administrator

Subject:
title
Approve and authorize Service Agreements with ECB Solutions, LLC and MVA Power, Inc. for the purchase of electrical switchgear and transformer equipment for the Central Library and authorize appropriation in the amount of $221,494
body

Statement of Issue:
On April 14, 2023, the electrical equipment that powers the Central Library failed, resulting in the Library's closure. A temporary generator has been in place while purchase of equipment to permanently fix the electrical equipment could be acquired. On July 18, 2024, bids were publicly opened for the Central Library Electrical Switchgear Replacement Project. City Council action is requested to award service agreements to ECB Solutions, LLC and MVA Power, Inc., the lowest responsive and responsible bidders for each piece of equipment.

Financial Impact:
The total cost of the equipment for this project is $221,494. Funds for this project are requested from the Infrastructure Fund (314) to be appropriated to business unit 31440040.82200.

Recommended Action:
recommendation
A) Approve the purchase of electrical switchgear and transformer equipment from ECB Solutions, LLC and MVA Power, Inc. in the amount of $221,494; and,

B) Authorize the Mayor and City Clerk to execute a Service Agreement between the City of Huntington Beach and ECB Solutions, LLC for the purchase of 3-phase padmount transformer; and,

C) Authorize the Mayor and City Clerk to execute a Service Agreement between the City of Huntington Beach and MVA Power, Inc. for the purchase of padmount switchgear; and,

D) Authorize the appropriation of $221,494 from the Infrastructure Fund (314) to business unit 31440040.82200.
end

Alternative Action(s):
Do not approve the recommended actions...

Click here for full text