REQUEST FOR CITY COUNCIL ACTION
SUBMITTED TO: Honorable Mayor and City Council Members
SUBMITTED BY: Travis Hopkins, City Manager
VIA: Chau Vu, Director of Public Works
PREPARED BY: Joseph Pinel, Capital Projects Administrator
Subject:
title
Accept the lowest responsive and responsible bid and authorize execution of a construction contract with Full Swing Construction Inc. in the amount of $1,099,477 for the Police Department Women's Locker Room Improvement Project, CC-1708; Reject bids 1-7; and Authorize 20% in contingency funds
body
Statement of Issue:
On April 7, 2025, the City of Huntington Beach publicly opened bids for the Police Department Women's Locker Room Improvement Project. Shortly thereafter, on April 11, 2025, a formal bid protest was submitted to the Public Works Department. Following a thorough investigation, it was determined that the bids in question did not meet the required contract specifications. In light of these findings, City Council action is requested to award the construction contract to Full Swing Construction Inc., identified as the lowest responsive and responsible bidder.
Financial Impact:
The estimated project cost is $1,319,372, which includes the construction contract with Full Swing Construction Inc., and a 20% construction contingency. The project budget $1,319,372 consists of Infrastructure Funds from Account No. 31440010.
Recommended Action:
recommendation
A) Accept the lowest and responsible bid submitted by Full Swing Construction Inc. in the amount of $1,099,477; and
B) Reject bids 1-7, as a result of formal bid protest; and
C) Authorize the Director of Public Works to Approve change orders up to 20% contingency in potential construction change orders; and
D) Authorize the Mayor and City Clerk to execute a construction contract with Full Swing Construction Inc. in a form approved by the City Attorney.
end
Alternative Action(s):
Reject all bids and provide staff with direction.