huntington beach banner
File #: 23-704   
Type: Consent Calendar Status: Passed
File created: 8/16/2023 In control: City Council/Public Financing Authority
On agenda: 9/5/2023 Final action: 9/5/2023
Title: Cancel contract award for the Humboldt Sewer Lift Station Replacement Project, CC-1634; reject all remaining bids and re-bid the project in accordance with City Charter requirements
Attachments: 1. Att #1 Location Map, 2. Att #2 Humbolt LS PP 09052023, 3. 9/5 Sup Com
REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Al Zelinka, City Manager

VIA: Alvin Papa, Acting Director of Public Works

PREPARED BY: John Dettle, Associate Engineer

Subject:
title
Cancel contract award for the Humboldt Sewer Lift Station Replacement Project, CC-1634; reject all remaining bids and re-bid the project in accordance with City Charter requirements
body

Statement of Issue:
On August 1, 2023, City Council awarded a construction contract to Mehta Mechanical Company, Inc. (Mehta) for the Humboldt Sewer Lift Station Replacement Project. However, it was later discovered that the bidding process was not consistent with City Charter requirements and State Law. As such, City Council action is requested to cancel the contract award to Mehta and reject all other bids, in order to properly re-advertise and rebid the Project.

Financial Impact:
There are no fiscal impacts related to the recommended action.

Recommended Action:
recommendation
Cancel the award of construction contract to Mehta for the Humboldt Sewer Lift Station Replacement Project, CC-1634; reject all remaining bids and rebid the project in accordance with City Charter requirements and State Law.
end

Alternative Action(s):
Do not accept the recommended action, and direct staff accordingly. Rejecting all bids and rebidding is required to comply with the City Charter.

Analysis:
Staff advertised the Humboldt Sewer Lift Station Replacement Project this summer on PlanetBids, an online platform used by a majority of public agencies to advertise project bids and requests for proposals/qualifications. The bids received via PlanetBids were appropriately evaluated, and on August 1, 2023, a construction contract was awarded to Mehta, the lowest and most responsive bidder.

However, staff did not confirm that the advertisement was also published in a locally circulated newspaper, as required under Charter Section 503. As such, sta...

Click here for full text