File #: 26-015   
Type: Consent Calendar Status: Passed
File created: 12/22/2025 In control: City Council/Public Financing Authority
On agenda: 1/20/2026 Final action: 1/20/2026
Title: Accept a Completion Bond for Building Improvements Associated with 21 and 22 Main Street on the Huntington Beach Pier
Attachments: 1. Att #1 Surf City Partners Bond, 2. Att #2 PowerPoint Presentation, 3. 1/15 Sup Com
REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Travis Hopkins, City Manager

VIA: Jennifer Villasenor, Director of Community Development

PREPARED BY: Kriss Casanova, Economic Development Manager

Subject:
title
Accept a Completion Bond for Building Improvements Associated with 21 and 22 Main Street on the Huntington Beach Pier
body

Statement of Issue:
City Council action is requested to accept a completion bond guaranteeing the completion of required improvements associated with the construction of a new restaurant project located at 21 and 22 Main Street on the Huntington Beach Pier. The completion bond is required under the executed sublease between the City and Surf City Partners, LLC (the "Lessee") and ensures that the approved improvements will be completed in accordance with approved plans, conditions of approval, applicable City standards, and regulatory requirements.

A completion bond is a financial guarantee that protects the City by ensuring that required improvements are completed, or that funds are available for the City to complete the work, in the event the Lessee fails to do so.

Financial Impact:
There is no direct fiscal impact to the City associated with acceptance of the completion bond. The bond serves as financial security to ensure completion of required improvements at no cost to the City in the event of default by the Lessee.

Recommended Action:
recommendation
A) Accept the Completion Bond in the amount of $1.3 million for building improvements associated with 21 and 22 Main Street; and

B) Authorize the City Engineer to administer and enforce the bond in accordance with City standards and applicable law.
end

Alternative Action(s):
Do not approve the recommended action and direct staff accordingly. If the completion bond is not accepted, construction of the project cannot proceed until an acceptable bond is approved by the City Council, resulting in a delay of the ...