REQUEST FOR CITY COUNCIL ACTION
SUBMITTED TO: Honorable Mayor and City Council Members
SUBMITTED BY: Travis Hopkins, City Manager
VIA: Chau Vu, Director of Public Works
PREPARED BY: Frank Drevdahl, Capital Projects Administrator
Subject:
title
Accept Lowest Responsive and Responsible Bid and Award a Construction Contract to Newbuild Construction and Restoration, Inc. in the amount of $628,600 for the Newland House Museum & Water Tower Restoration, CC1788
body
Statement of Issue:
At the September 15, 2026 City Council Meeting, staff was directed to return with updated information regarding the Newland House Museum & Water Tower Restoration Project (CC1788) for consideration at the October 6, 2026 City Council Meeting.
Bids for Newland House Museum & Water Tower Restoration, CC1788 were publicly opened on May 20, 2026. Staff recommends that the City Council accept the lowest responsive and responsible bid and award a construction contract to Newbuild Construction and Restoration, Inc. in the amount of $628,600.
Financial Impact:
The total project cost for the Newland House Museum & Water Tower Restoration is $673,080.40, as itemized below:
Item
Amount Base Bid submitted by Newbuild Construction and Restoration, Inc. $589,600.00 Additive Bid Amount (Newland Barn Painting) $39,000.00 Construction Contract Amount: $628,600.00 5% Contingency $31,430.00 Supplemental Project Costs (Architectural Historian) $10,000.00 Supplemental Project Costs (Material Testing) $3,050.40 Total Project Cost: $673,080.40
The available funding for this project is $571,965.60 from the Infrastructure Fund (314) in Account No. 31440023.82200. Staff is requesting that City Council appropriate additional funding in the amount of $101,114.80 from the Infrastructure Fund (314) to cover the total project cost. The requested appropriation will be funded from FY 2025-26 carryover funds creating a net zero impact to the Infrastructure Fund Balance.
Recommended Action:
re...