Title: Adopt Resolution No. 2024-05 certifying that the City has the resources to implement the projects to be included in the FY 2024/25 - FY 2029/30 Federal Transportation Improvement Program (FTIP) as required by the Orange County Transportation Authority (OCTA)
Attachments: 1. Att 1 Resolution No. 2024-05, 2. Att 2 PowerPoint Presentation
REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Eric G. Parra, Interim City Manager

VIA: Chau Vu, Director of Public Works

PREPARED BY: Jonathan Claudio, Senior Civil Engineer

Subject:
title
Adopt Resolution No. 2024-05 certifying that the City has the resources to implement the projects to be included in the FY 2024/25 - FY 2029/30 Federal Transportation Improvement Program (FTIP) as required by the Orange County Transportation Authority (OCTA)
body

Statement of Issue:
The Orange County Transportation Authority (OCTA) requires the submittal of a resolution certifying that the City has the resources to implement the projects to be included in the Federal Transportation Improvement Program (FTIP).

Financial Impact:
There is no fiscal impact.

Recommended Action:
recommendation
Adopt Resolution No. 2024-05, "A Resolution of the City Council of the City of Huntington Beach Certifying that the City has the Resources to Fund the Projects in the FY 2024/25 - 2029/30 Transportation Improvement Program and Affirms its Commitment to Implement All Projects in the Program."
end

Alternative Action(s):
Do not adopt the resolution, and do not receive FTIP funding through OCTA.

Analysis:
The City Council has committed local funding, in the past, to match federally funded grants through the Federal Transportation Improvement Program (FTIP), which is a database that includes projects that are programmed with state and federal funds as well as projects of regional significance. The following is a list of the City's both recently completed projects and future planned projects that are currently included in the FTIP:
1. Utica Avenue Bicycle Boulevard (Construction completed in FY 23/24)
2. Saybrook Lane Rehabilitation (Construction completed in FY 23/24)
3. Admiralty Drive Bridge Rehabilitation (Construction to begin by March 2024)
4. Humboldt Drive Bridge Rehabilitation (Construction tentatively scheduled ...