Skip to main content
huntington beach banner
File #: 25-935   
Type: Consent Calendar Status: Agenda Ready
File created: 11/26/2025 In control: City Council/Public Financing Authority
On agenda: 12/16/2025 Final action:
Title: Accept the lowest responsive and responsible bid and authorize execution of a construction contract with Harbour Constructors Co. in the amount of $152,300 for the Tide Check Valves within Huntington Harbour Project (CC-1774)
Attachments: 1. Att #1 RCA Contract Agreement Summary, 2. Att #2 Vicinity Map, 3. Att #3 Construction Contract, 4. Att #4 PowerPoint Presentation
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Travis Hopkins, City Manager

VIA: Chau Vu, Director of Public Works

PREPARED BY: Michelle Galvez, Environmental Specialist

Subject:
title
Accept the lowest responsive and responsible bid and authorize execution of a construction contract with Harbour Constructors Co. in the amount of $152,300 for the Tide Check Valves within Huntington Harbour Project (CC-1774)
body

Statement of Issue:
On October 30, 2025, bids were publicly opened for the Tide Check Valves within Huntington Harbour Project. City Council action is requested to award the construction contract to Harbour Constructors Co., the lowest responsive and responsible bidder.

Financial Impact:
Total cost for the project is $182,760 with the breakdown as follows:

Construction - Base Bid
$ 152,300
Contingency (20%)
$ 30,460
Total Project Cost
$ 182,760

Funds for this project are available in the current fiscal budget as follows:

Infrastructure Fund
Acct.
31440021
$ 182,760
Total Funds Available

$ 182,760


Recommended Action:
recommendation
A) Accept the lowest responsive and responsible bid submitted by Harbour Constructors Co., in the amount of $152,300 (Base Bid); and,

B) Authorize the Mayor and City Clerk to execute a construction contract in a form approved by the City Attorney.
end

Alternative Action(s):
Do not approve the recommended actions, and direct staff accordingly.

Analysis:
During king tide events, seawater flows back into the storm drain system, causing localized flooding. The existing flap and duckbill valves are no longer effective. This project consists of installing new in-line tide check valves at seven locations and removing outdated flap and duckbill gate valves. The purpose is to help reduce flooding during king tides by preventing tidal water from backing up into the storm drain system. All check valves will be installed within the existing storm drai...

Click here for full text