File #: 23-745   
Type: Consent Calendar Status: Passed
File created: 9/6/2023 In control: City Council/Public Financing Authority
On agenda: 9/19/2023 Final action: 9/19/2023
Title: Accept bid and authorize execution of a construction contract with Applied Restoration, Inc. in the amount of $754,451.80 for the construction of Goldenwest St. and Graham St. Bridge Maintenance Project, CC-1713
Attachments: 1. Att #1 Location Map (CC-1713), 2. Att #2 PowerPoint Presentation (CC-1713)
REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Al Zelinka, City Manager

VIA: Chau Vu, Director of Public Works

PREPARED BY: Jonathan Claudio, Senior Civil Engineer

Subject:
title
Accept bid and authorize execution of a construction contract with Applied Restoration, Inc. in the amount of $754,451.80 for the construction of Goldenwest St. and Graham St. Bridge Maintenance Project, CC-1713
body

Statement of Issue:
On August 17, 2023, bids were opened for the construction of the Goldenwest St. and Graham St. Bridge Maintenance Project, CC-1713. City Council action is requested to award the construction contract to Applied Restoration, Inc., the lowest responsive and responsible bidder.

Financial Impact:
Funds are available in the amount of $750,000 from Prop 42 Fund Account 21985202. Additionally, there is $100,000 available to be carried forward from previous FY 22-23 Prop 42 Fund Account 21985201.

Recommended Action:
recommendation
A) Accept the lowest responsive and responsible bid submitted by Applied Restoration, Inc. in the amount of $754,451.80; and,

B) Authorize the Mayor and City Clerk to execute a construction contract in a form approved by the City Attorney.
end

Alternative Action(s):
Reject all bids, and provide staff with alternative direction.

Analysis:
The project would include provide maintenance improvements to the Goldenwest St. and Graham St. Bridge including: removal and replacement of the concrete barriers and chain link fencing; replacement of joint seals in concrete sidewalk; removal and replacement of unsound concrete; repairing damaged wing wall; sealing bridge deck; removal and replacement of asphalt concrete pavement; waterproofing pier walls; removal of graffiti; and ancillary work as required. The proposed maintenance work aims to prolong the service life of these bridges in order to avoid more costly rehabilitation work in the future. Construction is plan...