REQUEST FOR CITY COUNCIL ACTION
SUBMITTED TO: Honorable Mayor and City Council Members
SUBMITTED BY: Travis Hopkins, City Manager
VIA: Chau Vu, Director of Public Works
PREPARED BY: Eduardo Okamoto-Cerda, Senior Civil Engineer
Subject:
title
Accept Lowest Responsive and Responsible Bid and Award Construction Contract to Beador Construction Company, Inc. in the Amount of $4,999,700 for the Humboldt Drive Bridge Rehabilitation Project (CC1451); Authorize a $729,300 Construction Contingency; and Approve the Appropriation of $3,385,000
body
Statement of Issue:
On January 22, 2026, the City of Huntington Beach publicly opened bids for the Humboldt Drive Bridge Rehabilitation Project (CC1451). City Council action is requested to accept the lowest responsive and responsible bid and award the construction contract to Beador Construction Company, Inc.
Financial Impact:
The total estimated project cost is $6,529,000, which includes the construction contract with Beador Construction Company, Inc. in the amount of $4,999,700, a $729,300 contingency, and $800,000 supplemental costs for construction support services and related project expenses.
The total cost of the Humboldt Drive Bridge Rehabilitation project is $6,529,000. The current project budget is a total of $3,144,000, which includes $2,814,000 in Highway Bridge Program funds (Account No. 96185002) and $330,000 in Water Fund (Account No. 50791054). In April 2026, the City secured additional federal grant funding from the Highway Bridge Program in the amount of $3,385,000 to fully fund the project. The project budget will be as follows:
Highway Bridge Program funds
$6,199,000
Water Fund
$330,000
Total Budget:
$6,529,000
City Council is requested to appropriate an additional federal grant funding of $3,385,000 for the Humboldt Drive Bridge Rehabilitation Project (CC1451) to fully fund the project.
Recommended Action:
recommendation
A) Accept the lowest responsive and responsible bid and award a co...
Click here for full text