DESIGN REVIEW BOARD STAFF REPORT
TO: Design Review Board
FROM: Joanna Cortez, Principal Planner
SUBJECT:
title
DESIGN REVIEW BOARD NO. 20-006 (GOLDENWEST/GARFIELD COMMERCIAL)
REQUEST:
To review updated design, colors, and materials of a proposed service station consisting of two canopies at an overall height of 19 ft., 14 pumps, a 233 sq. ft. payment kiosk at 13 ft. in height and a 3,588 sq. ft. drive-thru carwash at an overall height of 30 ft. with six vacuum stalls on a vacant site per Condition No. 5.b of Conditional Use Permit No. 19-021.
LOCATION:
19026 Goldenwest Street, 92648 (Southeast corner of Goldenwest Street and Garfield Avenue)
body
APPLICANT:
Eric Fitzer/Robert Cole, Sustainability Engineering Group, 5240 N. 16th Street, Phoenix, AZ 85016
PROPERTY
OWNER:
Garfield Goldenwest LLC, 19026 Goldenwest Street, Huntington Beach, CA 92648
STAFF RECOMMENDATION:
recommendation
That the Design Review Board take the following actions:
A) Recommend approval of Design Review No. 20-006 to the Director of Community Development.
end
General Plan:
I-sp (Industrial-Specific Plan Overlay)
Zone:
SP9 (Holly Seacliff Specific Plan)
Existing Use:
Vacant
ATTACHMENTS:
1. Suggested Conditions of Approval
2. Plans received and dated March 3, 2026