Skip to main content
huntington beach banner
File #: 25-936   
Type: Consent Calendar Status: Agenda Ready
File created: 11/26/2025 In control: City Council/Public Financing Authority
On agenda: 12/16/2025 Final action:
Title: Accept the lowest responsive and responsible bid and authorize execution of a construction contract with Wright Construction Engineering Corp. in the amount of $293,249 for the Bluff Top Slope Repair Project (CC-1815)
Attachments: 1. Att #1 Contract Agreement Summary, 2. Att #2 Construction Contract, 3. Att #3 Vicinity Map, 4. Att #4 PowerPoint Presentation
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

REQUEST FOR CITY COUNCIL ACTION

 

SUBMITTED TO:                     Honorable Mayor and City Council Members                     

 

SUBMITTED BY:                     Travis Hopkins, City Manager                     

 

VIA:                     Chau Vu, Director of Public Works

 

PREPARED BY:                     Michelle Galvez, Environmental Specialist

 

Subject:

title

Accept the lowest responsive and responsible bid and authorize execution of a construction contract with Wright Construction Engineering Corp. in the amount of $293,249 for the Bluff Top Slope Repair Project (CC-1815)

body

 

Statement of Issue:

On October 21, 2025, bids were publicly opened for the Bluff Top Slope Repair Project. City Council action is requested to award the construction contract to Wright Construction Engineering Corp., the lowest responsive and responsible bidder.

 

Financial Impact:

Total cost for the project is $402,236 with the breakdown as follows:

 

Construction - Base Bid

$ 293,249

Contingency (15%)

$   43,987

Materials, Testing, and Inspection Services

$   65,000

Total Project Cost

$ 402,236

 

Funds for this project are available in the current fiscal budget as follows:                                                                                    

 

Infrastructure Fund

Acct.

31490015

$ 402,236

Total Funds Available

 

$ 402,236

 

 

Recommended Action:

recommendation

A) Accept the lowest responsive and responsible bid submitted by Wright Construction Engineering Corp., in the amount of $293,249 (Base Bid); and,

 

B) Authorize the Mayor and City Clerk to execute a construction contract in a form approved by the City Attorney.

end

 

Alternative Action(s):

Do not approve the recommended actions, and direct staff accordingly.

 

Analysis:

The existing Bluff Top slope is showing signs of distress, including localized failures and surface erosion. One section between the two Dog Beach parking lots has already failed and requires reconstruction of approximately 77’ x 44’ of bluff top.

The project scope includes unclassified excavation with saw cutting, removal, and disposal of asphalt, vegetation, and miscellaneous debris. The slope will be rebuilt with slope benches and reinforced using Geogrid. Geogrid is a strong, mesh-like material used in construction to reinforce soil on slopes, retaining walls, and roadbeds.  It has a grid pattern with openings, so soil or rock can “lock” into the grid.  Geojute erosion-control fabric will be installed across the entire slope face and planted with drought-tolerant landscaping.

A new four-zone irrigation system will be installed, including a solar-powered controller (without cabinet), conduits, valves, and all associated appurtenances. The contractor will provide a point of connection and tap into the existing water line.

To complete the project, 4 inches of new asphalt will be paved over a compacted subgrade, and a new redwood header will be installed at the edge. Access to both the lower and upper beach paths will be maintained throughout construction.

Bids were opened on October 21, 2025, with the following results:

Bidder’s Name

Bid Amount

Wright Construction Engineering Corp.

$293,249

Oppenheimer National

$327,327.75

Jeremy Harris Construction Inc.

$334,646

Matcon General Engineering Inc.

$345,672.98

SJD&B, Inc.

$350,961

MDB General Engineering, Inc.

$354,596

Heed Engineering

$359,250

Capo A General Contracting

$368,271

Azas Engineering Inc.

$369,395

OrangeBlue General Contractors

$369,570

KASA Construction, Inc.

$407,640

Clarke Contracting Corporation

$431,635

HZS Engineering and Construction

$437,280

James McMinn, Inc.

$440,790

Ortiz & Son, Inc.

$447,313

Lonerock, Inc

$480,710

Premo Construction Inc.

$484,306

J/K Excavation & Grading Co., Inc.

$503,860

 

Staff recommends awarding a contract to Wright Construction Engineering Corp. in the amount of $293,249. Wright Construction Engineering Corp. has successfully completed similar construction projects in other cities. The total project cost is estimated at $402,236 which includes the construction contract, construction contingency, materials testing, and inspection.

 

 

Environmental Status:

This project is exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15031c under Class 1 of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a significant effect on the environment.

 

 

Strategic Plan Goal:

Non Applicable - Administrative Item

 

Attachment(s):

1.                     Contract Agreement Summary

2.                     Construction Contract

3.                     Vicinity Map

4.                     PowerPoint Presentation