REQUEST FOR CITY COUNCIL ACTION
SUBMITTED TO: Honorable Mayor and City Council Members
SUBMITTED BY: Oliver Chi, City Manager
PREPARED BY: Sean Crumby, Director of Public Works
Subject:
title
Accept the lowest responsive and responsible bid and authorize execution of a construction contract with Parsam Construction, Inc. in the amount of $515,000 for the Peck and Springdale Facility Improvements project, CC-1590
body
Statement of Issue:
On July 13th, 2021 bids were publically opened for the Peck and Springdale Facility Improvements project. City Council action is requested to award the construction contract to Parsam Construction, Inc., the lowest responsive and responsible bidder.
Financial Impact:
Total funds for the project, including contingency and supplemental expenses, is estimated at $618,000.00. Funds for the project are available in the current fiscal year budget in the Water Master Plan Fund, Account No. 50791005.82100.
Recommended Action:
recommendation
A) Accept the lowest responsive and responsible bid submitted by Parsam Construction Inc. in the amount of $515,000; and,
B) Authorize the Mayor and City Clerk to execute a construction contract in a form approved by the City Attorney.
end
Alternative Action(s):
Reject all bids, or provide staff with alternative action.
Analysis:
This project proposes to update and augment the existing system of fences and block walls that enclose the Peck and Springdale Reservoirs Site. The project will also install conduits for a future enhanced electronic security system at this site. The electronic security system is proposed to be constructed one year after the installation of the conduits. The Peck and Springdale Reservoir sites have two semi above ground reservoirs and three potable water wells. It is a critical site in providing the City with potable water. The site is unmanned, however City Water Production Staff visit the site on a daily basis. This project and the subsequent project will serve to safeguard this critical site.
Bids were publicly opened on July 13, 2021, with the following results:
BIDDER'S NAME |
BID AMOUNT (Amount Read at Bid Opening and Basis of Award) |
Parsam Construction Inc. |
$515,000 |
Amtek Construction |
$557,110 |
Ace Construction Inc. |
$587,500 |
Kazoni Construction |
$649,869 |
Staff recommends awarding a contract to Parsam Construction Inc. in the amount of $515,000.
Project reference checks have indicated that Parsam Construction Inc. has provided acceptable fence and conduit construction within the past year. The total project cost is estimated to be $618,000, which includes the construction contract ($515,000), contingency ($77,250), inspection and supplemental expenses ($25,750).
Environmental Status:
The project is categorically exempt pursuant to Class 1, section 15302.(c) of the California Environmental Quality Act.
Strategic Plan Goal:
Infrastructure & Parks
Attachment(s):
1. Project Vicinity Map