Legislation Details

File #: 26-407   
Type: Consent Calendar Status: Agenda Ready
File created: 4/28/2026 In control: City Council/Public Financing Authority
On agenda: 6/2/2026 Final action:
Title: Accept Lowest Responsive and Responsible Bid and Authorize Execution of a Construction Contract with Performance Pipeline Technologies, Inc., in the Amount of $1,970,231.60, for the FY 2025/26 Sewer Lining Project (CC-1845)
Attachments: 1. Att #1 RCA Contract Agreement Summary, 2. Att #2 Construction Contract - Performance Pipeline Technologies, 3. Att #3 PowerPoint Presentation
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

REQUEST FOR CITY COUNCIL ACTION

 

SUBMITTED TO:                     Honorable Mayor and City Council Members                     

 

SUBMITTED BY:                     Travis Hopkins, City Manager                     

 

VIA:                     Chau Vu, Director of Public Works

 

PREPARED BY:                     Michael Aguas, Capital Projects Administrator

 

Subject:

title

Accept Lowest Responsive and Responsible Bid and Authorize Execution of a Construction Contract with Performance Pipeline Technologies, Inc., in the Amount of $1,970,231.60, for the FY 2025/26 Sewer Lining Project (CC-1845)

body

 

Statement of Issue:

On March 26, 2026, the City received electronic bids via PlanetBids for the FY 2025/26 Sewer Lining Project. City Council action is requested to award the construction contract in the amount of $1,970,231.60 to Performance Pipeline Technologies, Inc., the lowest responsive and responsible bidder.

 

Financial Impact:

The total construction cost for the project, including 15% contingency, inspection, and testing is $2,365,766.34.

 

Item

Amount

Bid submitted by Performance Pipeline Technologies, Inc.

$1,970,231.60

15% Contingency

$295,534.74

Supplemental

$100,000.00

Total Construction Cost:

$2,365,766.34

 

 

Staff recommends awarding the construction contract to Performance Pipeline Technologies, Inc. in the amount of $1,970,231.60. Funding is available in the Fiscal Year 2025-26 budget in the Sewer Improvement Fund, Account No. 51189028.82600.

 

Recommended Action:

recommendation

A) Accept the lowest responsive and responsible bid submitted by Performance Pipeline Technologies, Inc. in the amount of $1,970,231.60; and,

 

B) Authorize the Director of Public Works to approve change orders up to 15% contingency in potential construction change orders; and,

 

C) Authorize the Mayor and City Clerk to execute the construction contract in a form approved by the City Attorney.

end

 

Alternative Action(s):

      1. Reject all bids.

      2. Direct staff to take alternative action.

 

Analysis:

The Engineering and Utilities Division identified the need for rehabilitation of existing sewer pipes based on maintenance history and video inspection. The scope of work for the project includes lining approximately 29,850 lineal feet of aged sewer main lines identified as a priority this year. The project locations would benefit from lining as the existing pipes contain calcium deposits resulting from groundwater seepage through minor cracks and joints, or have offset joints caused by tree root intrusion from adjacent mature trees located in parkways. These calcium deposits and roots inhibit sewage flow and will be removed prior to lining.

 

The lining process is a trenchless rehabilitation method in which a cured-in-place pipe (CIPP) UV liner is inserted into the existing pipe to form a new structural pipe within the existing pipe. The project also includes rehabilitation of 66 manholes.

 

Completion of this project will extend the service life of the sewer system by approximately 20 years, help prevent sanitary sewer overflows, reduce calcite buildup and groundwater inflow, and increase the structural integrity of the sewer infrastructure. Annual sewer lining projects preserve the life expectancy of critical citywide sewer utility infrastructure.

 

Bids were opened on March 26, 2026, with the following results:

 

Bidder’s Name

Bid Amount

Performance Pipeline Technologies, Inc.

$1,970,231.60

Vortex Services LLC, dba Sancon Technologies

$2,355,989.00

Tunnelworks Services Inc.

$2,377,552.00

Inliner Solutions, LLC

$3,024,825.00

 

Staff reviewed Performance Pipline Technologies, Inc. bid and determined it to be the lowest responsive and responsible bidder. Staff recommends awarding the Construction Contract to Performance Pipeline Technologies, Inc.

 

The total estimated project costs is $ $2,365,766.34, which includes the construction contract, 15% contingency, and supplemental costs for construction support services.

 

Environmental Status:

This project is exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15031c - Class 1 of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a significant effect on the environment.

 

Strategic Plan Goal:

Non Applicable - Administrative Item

 

For details, visit www.huntingtonbeachca.gov/strategicplan.

 

Attachment(s):

1.                     RCA Contract Agreement Summary

2.                     Construction Contract

3.                     PowerPoint Presentation