REQUEST FOR CITY COUNCIL ACTION

 

SUBMITTED TO:                     Honorable Mayor and City Council Members                     

 

SUBMITTED BY:                     Travis Hopkins, Acting City Manager                     

 

PREPARED BY:                     Jane Chung, Assistant to the City Manager

 

Subject:

title

FY 2023-2027 Strategic Plan - Biannual Progress Update #3

body

 

Statement of Issue:

Following City Council's adoption of the FY 2023-27 Strategic Plan on October 3, 2023, staff committed to providing biannual progress updates to the City Council in January and July. Progress updates ensure transparency and accountability towards the timely completion of the Strategic Plan, while giving City Council regular opportunities to review and recommend amendments, as needed. This report provides the third progress update.

 

Financial Impact:

Not applicable

 

Recommended Action:

recommendation

Receive and file the FY 2023-2027 Strategic Plan - Biannual Progress Update #3.

end

 

Alternative Action(s):

Do not approve the recommended action and direct staff accordingly.

 

Analysis:

From April to June 2023, the City Council and Executive Leadership Team underwent a comprehensive process to develop the FY 2023-2027 Strategic Plan (Plan). This process involved individual interviews with Council Members and Charter Officers, as well as workshops with the City Council and Department Heads to determine key priorities and projects for the next four fiscal years. The City Council adopted the Plan on October 3, 2023, through Resolution 2023-46.

 

The Strategic Plan includes eight overarching goals to be achieved through 23 major strategies and 98 tasks. Staff also identified over 70 key performance indicators (KPIs) to measure the Plan's impact over time. Staff has determined that the Plan is on track and successfully achieving its goals within the anticipated timeline. As of January 2025, the Plan is 53% complete, representing a 21% increase from the Second Biannual Progress Update in July 2024. Moreover, an additional 29% of the Plan is currently in progress, with 10% upcoming, and 7% on hold. To note, there has been an increase in on-hold tasks. This is due to staff identifying and implementing alternative cost-saving approaches to achieve the same objectives. These new strategies are expected to optimize resource utilization while maintaining the desired outcomes.

 

Following the second progress update, Staff has developed a public-facing data dashboard, now available on the City’s website. This dashboard details key performance indicators (KPIs) outlined in the Implementation Action Plan (Attachment 1). To note, the data is presented in calendar quarters, and some KPIs may have less available due to the limitations of the data sources.

 

The updated Implementation Action Plan provides detailed information, and a high-level summary is included in Attachment 2. Following tonight's meeting, all approved documents will be posted on the City's website at www.huntingtonbeachca.gov/strategicplan.

 

Environmental Status:

This action is not subject to the California Environmental Quality Act (CEQA) pursuant to Sections 15060(c)(2) (the activity will not result in a direct or reasonably foreseeable indirect physical change in the environment) and 15060(c)(3) (the activity is not a project as defined in Section 15378) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential for resulting in physical change to the environment, directly or indirectly.

 

Strategic Plan Goal:

Non Applicable - Administrative Item

 

For details, visit www.huntingtonbeachca.gov/strategicplan.

 