huntington beach banner
File #: 24-790   
Type: Consent Calendar Status: Agenda Ready
File created: 10/25/2024 In control: City Council/Public Financing Authority
On agenda: 12/17/2024 Final action:
Title: Approve and accept the Highway Bridge Program (HBP) grant funding from California Department of Transportation (Caltrans) for the Admiralty Drive Bridge Rehabilitation Project, CC-1450; and approve appropriation of funds.
Attachments: 1. Att #1 - Finance Letter, 2. Att #2 - Location Map, 3. Att #3 - PowerPoint Presentation
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

REQUEST FOR CITY COUNCIL ACTION

 

SUBMITTED TO:                     Honorable Mayor and City Council Members                     

 

SUBMITTED BY:                     Travis Hopkins, Acting City Manager

 

VIA:                     Chau Vu, Director of Public Works

 

PREPARED BY:                     Joseph Fuentes, Principal Civil Engineer

 

Subject:

title

Approve and accept the Highway Bridge Program (HBP) grant funding from California Department of Transportation (Caltrans) for the Admiralty Drive Bridge Rehabilitation Project, CC-1450; and approve appropriation of funds.

body

 

Statement of Issue:

On August 13, 2024, $1,916,490 of additional HBP grant funding was awarded for the construction of the Admiralty Drive Bridge Rehabilitation Project, CC-1450 (“Project”).  City Council action is requested to accept and approve the additional HBP funding into the City’s Highway Bridge Replacement & Rehab Account (HBRR) No. 96185001.82800.

 

Financial Impact:

The original estimated project cost is $5,880,000 which includes the construction contract with the contractor Beador, a 15% contingency, and supplemental expenses.  The previously awarded project budget includes $3,280,000 of federal grant funds in the HBRR Account No. 96185001.82800, $500,000 from the Infrastructure Fund in Account No. 31440005.82300, and $2,100,000 from the Measure M Fund No. 21390036.82300.  The additional grant funds of $1,916,490 will allow the City to save the Infrastructure and Measure M Funds for this project. 

 

Recommended Action:

recommendation

A)                     Approve and accept the Highway Bridge Program grant funding for $1,916,490; and

 

B)                     Approve appropriation of funds into the Highway Bridge Replacement & Rehab (HBRR) (Account No. 96185001.82800).

end

 

Alternative Action(s):

Do not approve the recommended action and direct staff accordingly.

 

Analysis:

The Admiralty Drive Bridge in Huntington Harbour is a steel girder bridge originally constructed in 1963 and seismically retrofitted in 1994.  The rehabilitation is underway for the bridge and work includes removal and replacement of the concrete barriers, street lighting, sidewalks, and bridge deck; cleaning and painting of I-girders and other steel members; replacement of bearings; removal and replacement of any unsound concrete that could expose internal reinforcement to outdoor elements; removal and replacement of water mainline pipe; construction of a temporary traffic signal system; utility relocation; and ancillary work as required.  Construction began in the fall of 2024 and is expected to conclude in the spring of 2025.

The total construction cost of this project is $5,880,000, which includes the Contractor’s bid price, contingency, and supplemental work.  The original HBRR grant included a total funding of $3,280,000.  Per Caltrans Local Assistance Program Guidelines, city staff submitted a cost change request and was approved for an additional $1,916,490 of HBRR funding.

 

Environmental Status:

Categorical Exclusion was approved on January 12, 2016, in compliance with NEPA.  Mitigated Negative Declaration No. 15-002 was approved on December 16, 2015, in compliance with CEQA.

 

Strategic Plan Goal:

Non Applicable - Administrative Item

 

Attachment(s):

1.                     Finance Letter

2.                     Location Map

3.                     PowerPoint Presentation