File #: 22-332    Version: 1
Type: Consent Calendar Status: Passed
File created: 4/7/2022 In control: City Council/Public Financing Authority
On agenda: 5/3/2022 Final action: 5/3/2022
Title: Accept bid and authorize the Mayor and City Clerk's execution of a construction contract with Ferreira Construction Co., Inc., dba Ferreira Coastal Construction Co., in the amount of $109,021 for the construction of Fiber Optic Communications from City Hall to the Utility Yard, CC-1646, and authorize change orders not to exceed 15 percent.
Attachments: 1. Att#1 Location Map - FO -City Hall to Utility Yard
REQUEST FOR CITY COUNCIL ACTION

SUBMITTED TO: Honorable Mayor and City Council Members

SUBMITTED BY: Sean Joyce, Interim City Manager

VIA: Sean Crumby, Director of Public Works

PREPARED BY: William Janusz, Principal Civil Engineer

Subject:
title
Accept bid and authorize the Mayor and City Clerk's execution of a construction contract with Ferreira Construction Co., Inc., dba Ferreira Coastal Construction Co., in the amount of $109,021 for the construction of Fiber Optic Communications from City Hall to the Utility Yard, CC-1646, and authorize change orders not to exceed 15 percent.
body

Statement of Issue:
On April 5, 2022, bids were opened for the construction of fiber optic communications from City Hall to the Utility Yard located at the intersection of Garfield Avenue and Huntington Street. City Council action is requested to award the construction contract to Ferreira Construction Co. Inc., dba Ferreira Costal Construction Co., the lowest responsive and responsible bidder, consistent with the FY21/22 Capital Improvement Program.

Financial Impact:
The funds needed for this project is $146,000. $168,000 has been approved within the FY 2021/22 Capital Improvement Program from the Water Administration Fund, Account Number 50685801.82800.

Recommended Action:
recommendation
A) Accept the lowest responsive and responsible bid submitted by Ferreira Construction Co. Inc., dba Ferreira Costal Construction Co., in the amount of $109,021; and,

B) Authorize the Mayor and City Clerk to execute a construction contract in a form approved by the City Attorney; and,

C) Authorize the Director of Public Works to execute change orders not to exceed a total of 15 percent of the contract construction costs, or $16,353.
end

Alternative Action(s):
Reject all bids and provide staff with alternative direction.

Analysis:
The Information Services Division of the Administrative Services Department, in consultation with the Public Works Department, identified ...