Title: Peck and Springdale Reservoirs Security Project, Fences and Conduit, CC-1590
Attachments: 1. Peck and Springdale Security Vicinity Map.pdf, 2. Attachment 2 11 X 17.pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

PUBLIC WORKS COMMISSION

REQUEST FOR ACTION

 

                                                                                                                                                                                                                  

SUBMITTED TO:                     Chairman and Members of the Commission

 

SUBMITTED BY:                     Sean Crumby, PE, Director of Public Works

 

Subject:

title

Peck and Springdale Reservoirs Security Project, Fences and Conduit, CC-1590

body

 

Statement of Issue:

Plans and Specifications for the Peck and Springdale Reservoirs Security Project, Fences and Conduit, CC-1590, are in final preparation.  Staff requests approval that the subject project is in general conformance with the previously approved CIP.

 

Funding Source:

Funds in the amount of $400,000 have been budgeted from the Water Master Plan Fund account number 50791005.

 

Recommended Action:

recommendation

Motion to approve that the Peck and Springdale Reservoirs Security Project, Fences and Conduit, CC-1590 is in general conformance with the previously approved CIP.

end

 

Alternative Action(s):

Deny approval and recommend an alternative action.

 

Analysis:

This project proposes to update and augment the existing system of fences and block walls that enclose the Peck and Springdale Reservoirs Site.  The project will also install conduits for a future electronic security system at this site.  The electronic security system is proposed to be constructed one year after the installation of the conduits.  The Peck and Springdale Reservoir sites have two semi above ground reservoirs and three potable water wells.  It is a critical site in providing the City with potable water.  The site is unmanned, however City Water Production Staff visit the site on a daily basis.  This project and the subsequent project will serve to safeguard this critical site.

 

Attachment(s):

1.                     Vicinity Map

2.                     CC 1590 Peck and Springdale Reservoirs Security Project, Plans, (Preliminary)