Title: Zone 3 Residential Overlay Project, CC 1618.
Attachments: 1. Zone 3 Overlay Vicinty Map and Street List
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

PUBLIC WORKS COMMISSION

REQUEST FOR ACTION

 

                                                                                                                                                                                                                  

SUBMITTED TO:                     Chairman and Members of the Commission

 

SUBMITTED BY:                     Sean Crumby, PE, Director of Public Works

 

Subject:

title

Zone 3 Residential Overlay Project, CC 1618.

body

 

Statement of Issue:

Plans and Specifications for the Zone 3 Residential Overlay Project, CC-1618, have been finalized.

 

Funding Source:

Total funds in the amount of $3,100,000 have been budgeted for the project.  This includes $2,350,000 budgeted in the Gas Tax Fund and $500,000 in the Measure M Fund.  In addition, funds of $100,000 are budgeted in the Sewer Fund and $150,000 is budgeted in the Water Fund.                     .

 

Recommended Action:

recommendation

Motion to approve that the Zone 3 Residential Overlay Project, CC- 1618, is in general conformance with the previously approved CIP.

end

 

Alternative Action(s):

Deny approval and recommend an alternative action.

 

Analysis:

This project will rehabilitate approximately 121 of the worst residential street segments in Maintenance Zone 3. Maintenance Zone 3 is located in the central-east area of the City and generally includes streets north of Indianapolis Ave., east of Newland St., west of Bushard St., and south of Garfield Ave. Work will  include limited localized pavement repairs, crack sealing, tapered cold milling, striping, and new asphalt overlay. The Engineer’s Estimate for this project is $2,900,000.

 

 Attachment(s):

1.                     Location Map.