Adopt Resolution No. 2021-09 authorizing the Director of Public Works to request a project delay from the Orange County Transportation Authority (OCTA) for the commencement of the Bolsa Chica Street/Valley View Street Corridor Project
body
Statement of Issue:
In October 2019, the City of Huntington Beach in conjunction with the City of Westminster and the City of Garden Grove submitted an application to OCTA for a Regional Traffic Signal Synchronization Program project on Valley View Street/Bolsa Chica Street from Chapman Avenue in Garden Grove to Warner Avenue in Huntington Beach. COVID-related staffing and budget concerns among the participating agencies have led to the need to request a delay from OCTA for the commencement of this project. Program requirements for the OCTA grant state that the request to delay commencement of a project must be authorized by the City Council.
Financial Impact:
No funding is required for this action.
Recommended Action:
recommendation
Adopt Resolution No. 2021-09, "A Resolution of the City Council of the City of Huntington Beach Authorizing a Request to Pursue a Project Delay from the Orange County Transportation Authority (OCTA) for the Bolsa Chica Street/Valley View Street Corridor Project - Project P Regional Traffic Signal Synchronization Program - Comprehensive Transportation Funding Program."
end
Alternative Action(s):
Do not authorize the Director of Public Works to request a project delay. This alternative action may result in the loss of the grant funds for the project.
Analysis:
In October 2019, the City of Huntington Beach, the City of Westminster and the City of Garden Grove, jointly submitted an application to OCTA for a Regional Traffic Signal Synchronization Program project on Valley View Street/Bolsa Chic...