Title: Alley Rehabilitation (North of Heil Avenue between Graham Street and Springdale Street), CC-1569.
Attachments: 1. CC-1569 LOCATION MAP
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

PUBLIC WORKS COMMISSION

REQUEST FOR ACTION

 

                                                                                                                                                                                                                  

SUBMITTED TO:                     Chairman and Members of the Commission

 

SUBMITTED BY:                     Travis K. Hopkins, PE, Director of Public Works

 

Subject:

title

Alley Rehabilitation (North of Heil Avenue between Graham Street and Springdale Street), CC-1569.

body

 

Statement of Issue:

Plans and Specifications for the Alley Rehabilitation, CC-1569, are in final preparation and staff is seeking support to begin the public bidding process.

 

Funding Source:

The project construction cost is estimated at $500,000.  These funds have been budgeted and are available from the Infrastructure Fund Account 31440001.82800.

 

Impact on Future Maintenance Costs:  The proposed project will minimize future maintenance costs of this alley.

 

Recommended Action:

recommendation

Motion to approve that the Alley Rehabilitation Project, CC-1569, is in general conformance with the previously approved Capital Improvement Program.

end

 

Alternative Action(s):

Deny approval and recommend an alternative action.

 

Analysis:

The City hired a consultant to evaluate the condition of all publicly maintained alleys utilizing the same methodology in the City’s adopted Pavement Management Program.  The consultant determined that the subject alley, located north of Heil Avenue between Graham Street and Springdale Street, had the worst Pavement Condition Index (PCI=4) of the alleys surveyed.  For reference purposes, PCI values ranging between 86 and 100 are considered to be in “Very Good” condition; whereas PCI values between 0 and 40 are considered to be in “Very Poor” condition.

 

The project’s scope of work will be to remove and replace the existing asphalt concrete pavement and concrete v-gutter, with ancillary work as necessary.

 